9 Bridges Parapets completed for Hampshire County Council

 

Rhinoceros ICATS trained operatives completed the stripping and repainting of bridge parapets on 9 bridges across the county today. All previous coatings were removed by hand and mechanical abrading without blast cleaning and without contamination of the environment. Five coats of International Interseal 670 and Interthane 990 paints were applied by brush, HA items 115,116 and 168. Final dft readings were 350-400 microns, ensuring a loing life for these coatings. The works has been completed within budget and ahead of schedule. The paint inspector and client, (HCC) are very pleased with the high standard of workmanship achieved. This is the second contract we have completed for Hampshire County Council.